天天干天天操天天射_蜜桃网址_japanxxxvideo_97久久人人爽人人爽人人

EN
The flue gas cleaning project of Phase III of Cixi household waste incineration power generation project in Ningbo city, Zhejiang province, which was constructed by Huaxing East, passed 72+24 hours trial operation
2024.03.29
The third phase of flue gas cleaning project of Cixi household waste incineration power generation project in Ningbo city, Zhejiang province undertaken by our company passed 72+24 hours trial operation on November 20th, 2023.
The project is designed to incinerate 750 tons of domestic waste per day, with a reserved construction site for a 750t/d mechanical grate waste incineration line and a supporting flue gas cleaning treatment line. This flue gas cleaning process adopts "PNCR+SDA semi-dry method + activated carbon injection + dry injection + bag dust collector + 1#GGH + wet deacidification + 2#GGH + SGH + low-temperature SCR + fly ash transportation, storage and stabilization process" This flue gas cleaning process is our EPC project.
Huaxing East's performance in Zhejiang Province includes: Ningbo Dongqiao, Ningbo Cixi Phase I, II, III, Ningbo Yinzhou, Lanxi, Shaoxing Shangyu, Lishui, Lishui Qingtian, Huzhou Deqing, Huzhou Anji, Ningbo Fenghua, Hangzhou Jiande , Jinhua, Jiaxing, Jiaxing Haiyan, Jiaxing Haining, Wenzhou Pingyang, Wenzhou Yongjia, Quzhou Longyou, Taizhou, Taizhou Wenling and other projects.

Click or scan below for more information!

Follow us!